Rule zero: Never work under or near ground you have not inspected and made safe.
| Field | Detail |
|---|---|
| Company / site | Ridgeline Copper Operations (fictional sample company) |
| Document No. | SOP-MIN-003 |
| Revision | 1.0 (approved) |
| Effective | 2026-10-06 |
| Next review due | 2027-10-06 (or after any incident or change) |
| Applies to | Everyone who works in or near pit walls, benches, stopes, headings and stockpiles |
| Owner | Geotechnical Engineer |
| Approved by | Mine Manager and Site Safety Manager |
To prevent injury and equipment loss from falls of ground, rockfalls, wall failures and stockpile collapse, by inspecting, monitoring and controlling ground conditions.
Open pit benches and walls, underground headings and stopes, waste dumps and stockpiles.
| Role | Responsibilities |
|---|---|
| Geotechnical Engineer | Sets ground and slope design, monitoring triggers and exclusion rules. |
| Supervisor | Runs the ground examination, applies restrictions, stops work when triggers are reached. |
| Operators | Examine their workplace, report cracks, loose rock, water and movement. |
| Surveyors | Monitor slope prisms, radar or extensometers and report trend changes. |
| Hazard | Control |
|---|---|
| Loose rock and falls of ground | Scaling, bolting, mesh, barring down, exclusion until supported |
| Pit wall or bench failure | Berms, catch benches, slope monitoring with trigger levels, exclusion below active areas |
| Water and weather | Drainage control, stop-work after heavy rain until re-inspected |
| Stockpile and dump collapse | Limits on height and angle, no work below an active face, dump edge berms |
| Parameter | Value at Ridgeline Copper Mine |
|---|---|
| Bench design | 15 m bench height, 8 m berm width, 65 degree face angle in fresh rock |
| Slope radar | 2 radar units on the Alpha Pit north and east walls, readings reviewed every shift |
| Trigger levels | Alert 4 mm/h, Action 8 mm/h, Evacuate 15 mm/h sustained for 30 minutes |
| Rain stop-work | More than 25 mm in 24 hours: re-inspect the walls before work resumes below any bench |
| Underground support | Pattern bolts at 2.0 m spacing, 2.4 m split-sets with mesh to 2.5 m above the floor in drive intersections |
| Dump limits | Waste dump lift height 30 m; no work below an active dump face |
Stop the job, make the area safe and call the supervisor if any of these happen:
Controlled document. The current version lives in this library. Printed copies are uncontrolled: check the revision before you use one. Questions or improvements go to the document owner.
| Rev | Date | Author | Change |
|---|---|---|---|
| 1.0 | 2026-10-06 | Site HSE department | First issue, approved for use |